State approvals / Andhra Pradesh / Department of Energy
Final approval from Electrical Inspector
This approval is required by every owner of an electrical installation planning for an installation voltage of 33KV and above.
DepartmentDepartment of Energy
TypeNew
StagePre-Operation
Time limit7 working days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Form-A Test Certificates of: Transformers, Isolators, Lightning Arresters, Current Transformers, Potential Transformers, EHV/HV/LV Breakers, Cables Load particulars (EHV, HV, MV, LV and Lighting) (Describing makers name, makers s.no, capacity andv oltage) No. of towers and type Type and length of conductor Pre commissioning test reports | — | Required |
More from Department of Energy
- Electrical Inspectorate statutory approval for drawings for 33 Kv and above
- Final Approval for DG set installation
- Initial Inspection of Generating Set
- Initial Inspection of High Extra High Voltage Installation
- Initial Inspection of Low Voltage Installation
- Initial Inspection of Medium Pressure Installation
- Power Feasibility certificate sanction of power supply
- Sanction of Estimate/Issuance of Service Connection for Power Supply for 11KV or 33KV
- Sanction of Estimate/Issuance of Service Connection for Power Supply for 11KV or 33KV - RESCO
- Sanction of Estimate/Issuance of Service Connection for Power Supply for 132KV or 220KV