State approvals / Andhra Pradesh / Factories department
Factory Plan approval under Factories Act, 1948
This license is required for more than or equal to 20 workers with use of power or more than or equal to 40 workers without use of power.
DepartmentFactories department
TypeNew
StagePre-Establishment
Time limit7 working days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Site Plan drawn to a scale of 1:400/1:800/ 1:1200 (metric), showing the details of neighborhood, location of all building/ sheds, Plant & M/c, storages, etc., access road indicating its width. The site plan should indicate front, rear and side setbacks clearly. North direction should be indicated in the site plan. 2. Detailed plans drawn to a scale of 1:100 (metric) (Plan, elevation & sectional view) of the proposed factory sheds/buildings, plant & m/c, storages, etc., showing the layout and type of machinery proposed to be installed in the particular shed with horsepower. Material to be used for the construction of building and roofing to be specified. 3. Detailed process description 4. In case of Revised Application, please provide copy of relevant latest Plan Approval 5. Ownership documents / registered lease deed of the site, in case of APIIC land the position certificate issued by APIIC 6. Units with Hazardous chemicals (as prescribed under MSIHC Rules, 1989) shall enclose appropriate Hazard Analysis & Risk Assessment report, details of Hazardous processes, quantities of chemicals, Consequence analysis etc. 7. Clearance from the explosive authorities is necessary wherever materials attracting the provisions of explosives act are handled /processed/stored | — | Required |