State approvals / Assam / Public Works Roads Department

Grant of Right of Way permission (RoW)

This permission is required for making a way over a piece of land usually to and from another piece of land.

DepartmentPublic Works Roads Department
TypeNew
StagePre-Operation
Time limit30 Days
FeeNo fee
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 A Copy of Feasibility report from APDCL (in case of overhead power line only) — Required
2 A Copy of Authorization Letter from all partners/ directors authorizing the applicant — Required
3 A Copy of PAN of the Enterprise — Required
4 A Copy of Copy of the License of the authorization Contractor — Required
5 UBIN Certificate — Required