Application for demand of water for industrial use from GWIL/SSNNL/Water Resources Department

This approval is required to apply for water requirement for industrial use from GWIL/SSNNL/Water Resources Deaprtment

DepartmentWater Resources Department
TypeNew
StagePre-Establishment
Time limit60 Days
FeeFee as notified by the department
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 Approval from Industries Commissioner — Required
2 Documents supporting water requirement as per industrial process — Required
3 Document mentioning approved quantity of the present source — Required
4 Small plan of the key location — Required
5 Documents if permission of water for the present project was taken before — Required
6 Documents if industry has got permission with other name — Required
7 Documents if the permission is cancelled, then give details — Required
8 Documents if any court case filed with SSNNL/GWIL/Water Resources Dept. of other authority regarding recovery of water charges — Required