State approvals / Gujarat / Water Resources Department
Application for demand of water for industrial use from GWIL/SSNNL/Water Resources Department
This approval is required to apply for water requirement for industrial use from GWIL/SSNNL/Water Resources Deaprtment
DepartmentWater Resources Department
TypeNew
StagePre-Establishment
Time limit60 Days
FeeFee as notified by the department
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Approval from Industries Commissioner | — | Required |
| 2 | Documents supporting water requirement as per industrial process | — | Required |
| 3 | Document mentioning approved quantity of the present source | — | Required |
| 4 | Small plan of the key location | — | Required |
| 5 | Documents if permission of water for the present project was taken before | — | Required |
| 6 | Documents if industry has got permission with other name | — | Required |
| 7 | Documents if the permission is cancelled, then give details | — | Required |
| 8 | Documents if any court case filed with SSNNL/GWIL/Water Resources Dept. of other authority regarding recovery of water charges | — | Required |