Boiler Registration under Boilers Act 1923

This approval is required by the owner of boiler to apply for the permission for erection of new boiler indicating the Inspecting Authority [as defined in Section 2(ccd) of the Boilers Act, 1923] and recognised as such by the Central Boiler Board under Indian Boilers Regulations, 1950 which will inspect the boiler during erection.

DepartmentDepartment of Industries
TypeNew
StagePre-Operation
Time limit34 days
FeeNo fee
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 A scanned copy of the certificate of approved Boiler repairer engaged for boiler erection. A scanned copy of steamline drawings in isometric view indicating type of welding to be done and bill of material duly signed by the owner of boiler and the Design Engineer who designed the steamline. A scanned copy of the IBR approved welder certificate who will be engaged for welding work. A scanned copy/digitally signed Boiler Folder (Form-II) as supplied by the Boiler Manufacturer and duly approved by the Inspecting Authority of the Concerned State consisting of followings: - i. Form-II(1) {Regulation-4(c )(i)}., ii. Form-III constructors Certificate of Manufacture and Test for Boiler and Boiler components {Regulation-4(c )(ii)}., )}., iii. Form-III-C Certificates of manufacture and test of Boiler Mountings and Fittings Regulation-4(g), iv. Form-IV-A Certificates of manufacture and results of test in lieu of original test certificates {Regulation-4(c) (iv)}. v. Scanned copies of drawings for boiler and boiler parts, mountings/accessories. vi. Test certificates of pipes and fittings — Required

More from Department of Industries