State approvals / Kerala / Electrical Inspectorate
Electrical Scheme Approval
DepartmentElectrical Inspectorate
TypeNew
StagePre-Operation
Time limit10 days (For industries with connected load less than 1 MW), others 30 days
FeeNo fee
Applied—
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | A covering letter, with court fee stamp worth INR 1/- affixed. 2. Authorization Letter from the client authorizing the Electrical contractor to carry out the work giving brief particulars of the scheme, drawings, enclosures 3. Copy of the Electrical contractors License 4. Calculation of scrutiny fee 5. Soil Resistivity Certificate (only for HT Installations) 6. Original Challan/ Receipt of remittance 7. Fault level calculation (only for HT Installations) 8. Earthing calculation (only for HT Installations) 9. Bus Duct design (only for HT Installations) 10. Schematic drawings 11. A/C Calculations | If applicable | If applicable |