State approvals / Manipur / Manipur State Power Distribution Company Ltd. (MSPDCL)

Obtaining Power feasibility certificate or sanction of power supply under Electricity Act, 2003

DepartmentManipur State Power Distribution Company Ltd. (MSPDCL)
TypeNew
StagePre-Operation
Time limit10-12 Working Days
FeeNo fee
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 New Connection Application Form — Required
2 Wiring Diagram/SLD/ Site Plan showing internal wiring layout, main switch, meter location, earthing arrangement and nearest point of supply-duly certified by a Licensed Electrical Contractor (LEC) — Required
3 Certified List of appliances/machinery with contracted load and ratings, duly certified by a Licensed Electrical Contractor (LEC) — Required
4 Project report/Purpose details — Required