State approvals / Odisha / Department of Energy (Central Electricity Supply Utility of Odisha)
Certification of Electrical Installation
DepartmentDepartment of Energy (Central Electricity Supply Utility of Odisha)
TypeNew
StagePre-Operation
Time limit35 days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Drawing approval order from the Engineer-in-Chief (Electricity) 2. Details of Equipment 3. Completion Certificate against the work from a licensed electrical contractor of appropriate category. 4. Permission letter of concerned DisCom division for power supply to the proposed work 5. Test certificate of the Transformer 6. Factory test reports of each equipment 7. Field test report for each equipment 8. Transformer oil test report from Standard Testing Laboratory 9. Copy of test reports from Standard Testing Laboratory for CT, PT and Energy meter used to record the units generated | In case of generator | If applicable |
