State approvals / Telangana / Labour, Employment Training and Factories department
Factory plan approval from Director of Factories
This approval is required for the factories having a power requirement >10000 HP from the Deputy Chief inspector of factories
DepartmentLabour, Employment Training and Factories department
TypeNew
StagePre-Establishment
Time limit7 days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Registered sale deed/ Lease deed | — | Required |
| 2 | Site plan | — | Required |
| 3 | Detailed building plan | — | Required |
| 4 | Partnership deed/ Articles of Association | — | Required |
| 5 | Process flow chart | — | Required |
| 6 | Copy of PAN card / Aadhar card | — | Required |
| 7 | Previously approved plans and R No. of the Factory | In case of additional construction or installation of machinery | If applicable |