Electrical Drawing Approval from Electrical Inspectorate
This approval is required for using HT meter above 70k from the Electrical Inspectorate
DepartmentEnergy Department
TypeNew
StagePre-Establishment
Time limit14 days
FeeVaries with the application
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Agreement letter between Contractor and Owner | — | Required |
| 2 | Contractor License Copy | — | Required |
| 3 | Supervisor permit copy of the electrical in charge of the company | — | Required |
| 4 | Electrical single line diagram from point of commencement of supply to the end use of electrical energy | — | Required |
| 5 | The structural layout showing plan and elevations with sectional and safe clearances | — | Required |