State approvals / Tripura / Tripura State Electricity Corporation Ltd.
Application for Permanent Power Connection (CFO)
DepartmentTripura State Electricity Corporation Ltd.
TypeNew
StagePre-Operation
FeeVaries with the application
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Proof of the user's identity, | — | Required |
| 2 | Proof of ownership or occupancy (in the case of an owned or leased premise), | — | Required |
| 3 | Authorization document (in the case of a firm or company) | — | Required |
More from Tripura State Electricity Corporation Ltd.
- Application for Estimation of Power Connectivity - LT
- Application for Estimation of Power Connectivity HT/EHT (CFO)
- Application for Estimation of Temporary Connectivity (CFE)
- Application for Temporary Power Connection (CFE)
- CEIG/CEA Approvals of Switchyard Equipment & Transmission Line
- Permission to shift/build around existing utilities-Electrical Infrastructure (Transmission Lines)
- Permit for construction of transmission line
- Power Evacuation Arrangement
- Power line Crossings for 132 kV lines and above