Insights into Company Bills & Payments

State approvals / Uttarakhand / Uttarakhand Pollution Control Board

Consolidated consent & authorization under Water Act, 1974, Air Act, 1981 & authorization under the Hazardous and Other Wastes (Management and Transboundary Movement) Rules - expansion

DepartmentUttarakhand Pollution Control Board
TypeAmendment - Others
StagePre-Operation
AppliedIntegrated With SWCS
Unit sizeMicro, Small, Medium, Large, Mega, Ultra-Mega, Super Ultra-Mega
Business locationUrban-Plain, Urban-Hilly, Rural-Plain, Rural-Hilly
Risk / pollution categoryGreen Red
Investor typeForeign, Domestic

Documents to submit

#DocumentConditionRequired
1 Land allotment letter, LOI Authenticity of land ownership Documents for obtaining Consent to Establish (CTE) If applicable
2 Layout Plan of the project/industry site Layout of the project/ industry plan 3. Project report including complete details of raw materials (per month), production capacity (per month) and proposed investment Detailed Project Report 4. Manufacturing process along with detailed process flow chart Manufacturing process flow 5. Article of Association , M emorandum of Understanding AoA, MoU 6. Proposal for waste water treatment & disposal along with details of water consumption, wastewater generation & installed capacity of treatment system (KLD), along with adequacy report Water treatment & disposal plan with minute detailing 7. Proposal for Air Pollution Control measures along with fuel types and daily consumption Proposal for Air Pollution Control measures Documents for obtaining Consent to Establish (CTE) If applicable
3 Hazardous Waste/ E - Waste - Management Plan HWM / E - waste management & handling plan Documents for obtaining Consent to Establish (CTE) If applicable
4 Permission of CGWA Permission from CGWA 10. Mining Plan including Mining lease approval Valid Mining Plan & Lease 11. Environmental Clearance for prescribed authorization EC from MoEF, GoI S. No. Document Name Document check point 1. ETP/ STP final outlet analysis reports from notified laboratories (in case of Renewal/ Expansion) Analysis report of ETP/ STP (compliant) 2. Stack/ Ambient Air Quality Monitoring Report (in case of Renewal) from notified laboratories Stack/ Ambient Air Quality Monitoring Report (compliant) If applicable If applicable
5 Copy of CTE/ CCA issued & its Compliance Status Valid CTE/ CCA with compliance 4. Pointwise compliance of CCA conditions (In case of Renewal/ Expansion) and CTE (In case of CCA - fresh) Detailed Compliance Status as prescribed in NOC granted 5. Latest Audited Balance Sheet of the unit indicating fixed assets, current assets and current liabilities of the unit (prescribed format) CA certified balance sheet 6. List of hazardous waste generated along with Form - 4 & Form - 3 of Hazardous Waste Rules Form - 10 Detailed list of hazardous wastes Documents for Consolidated Consent & Authorization (CCA) If applicable
6 Details of SLF/TSDF/CBWTF Secured Land Field, Treatment, Storage & Disposal Facility , Common Biomedical Waste Treatment Facilities If applicable If applicable
7 Environmental Statement (Form - V) Compliant & authenticated Environmental Statement Documents for Consolidated Consent & Authorization (CCA) If applicable
  • Page 1 of 1 Document Checklist – UEPPCB Services Documents required for obtaining the Consent/Authorisation from the Uttarakhand Environment Protection & Pollution Control Board under section - 25 of Water (Prevention and Control of Pollution) Act, 1974, under section - 21 of Air (Prevention and Control of Pollution) Act, 1981 and authorization under Rule - 6 of the Hazardous and other Waste (Management and Transboundary Movement) Rules, 2016 made as per the provisions of the Environme nt (Protection) Act, 1986, are as follows: S. No. Document Name Document check point