Insights into Company Bills & Payments

State approvals / Assam / Inspectorate of Electricity

Approval for commencement of power supply in the electrical installations of multi-storied building

This approval is required for commencement of power supply to the multi-stored buildings (height more than 15 meters)

DepartmentInspectorate of Electricity
TypeNew
StagePre-Operation
Time limit15 days
FeeNo fee
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 Electrical lay out drawings that show the appropriate rating / type / size(s) of all electrical Generators, equipments, accessories, etc. in the single line diagram and dimensions / clearances etc. in the physical layout plan & in the details of earthing layout plan including panels, Lightening arrestor — Required
2 A details load schedule of the connected load and test report of the internal electrical installation including earth system with due seal and signature of contractor /authorized person(s) and countersigned by the consumer / owner / occupier or its agent — Required
3 A copy of permission / NOC for construction of the building along with approved drawing from Municipal / Development / Appropriate local Authority — Required
4 Certified copy of approved drawing and NOC to construct the building and completion certificate to be enclosed — Required
5 Connected load with break up of lighting, powers and others type of load in annexed sheet — Required
6 Distribution System details:(A single line diagram clearly indicating all devices, controls, connection, with all ratings and specification to be furnished. Load in each sub-circuit to be shown. In case of individual flats/ units having similar connections and electrical loads, details of one unit of each type only need to be furnished) — Required
7 Physical layout plan indicating the position of the transformer, panels, generator, route of all OH line/cables with dimensions/clearances — Required
8 Position of Main Control Room/Breakers/MCCBs/MCB, DB & electrical cable ducts and layout of main cable(s) — Required
9 A single line diagram of the main panel(s) indicating all connections and control/protective and metering equipment/devices with ratings and specifications — Required
10 A front view of the panel(s) indicating all equipment/devices — Required
11 A Test Report of the panel duly signed by the Electrical Supervisor of the manufacturer who has manufactured the electrical panel(s) — Required
12 Details of earthing (A layout of earthing of the main panel and other equipment to be furnished in the diagram required under 7.4 above.) — Required
13 Has lightning protection been provided:?Detailed diagram of lightening protection to be provided separately — Required
14 Furnish details of fire protection/fire alarm system provided. NOC of state fire department to be furnished — Required
15 Testing. A detailed test report with circuit wise insulation resistance and details of earth resistance test to be furnished. (Separately for each section, each panel and each unit/conductor) — Required