State approvals / Assam / Inspectorate of Boilers

Registration and Certification of Package Boiler/Economizer Form 1

DepartmentInspectorate of Boilers
TypeNew
StagePre-Operation
Time limit63 days
FeeVaries with the application
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 Form-II issued by the inspecting authority — Required
2 Form-III issued by the inspecting authority — Required
3 Form-IV A for all materials used for the Boiler — Required
4 Form-III C for all valves, mountings and fittings — Required
5 IBR approved details drawing of boiler — Required
6 All pressure parts assemble drawing — Required
7 ii. Welding details drawing — Required
8 iii. Manhole and head hole drawing — Required
9 iv. Feed pipeline and blow down detail drawings — Required