State approvals / Madhya Pradesh / Energy Department
Approval for new service connection HT Central Discom
This approval is required for distribution and supply of HT electricity connection. It shall be the duty of a distribution licensee to develop and maintain an efficient, co-ordinated and economical distribution system in his/her area of supply. Licensee, shall, on an application by the owner or occupier of any premises, give supply of electricity to such premises, within one month after receipt of the application requiring such supply
DepartmentEnergy Department
TypeNew
StagePre-Establishment
Time limit7 Days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | ID Proof of the Applicant 2. Letter of Authorization (in case of Company) 3. Ownership proof of Premises 1. ID Proof of the Applicant 2. Letter of Authorization (in case of Company) 3. Ownership proof of Premises | — | Required |
More from Energy Department
- Application for Drawing Approval Under Electrical Installation HV/EHV/ Diesel Generator/Non-Conventional
- Application for Inspection and Approval of HV/EHV/Diesel Generator/Non-conventional Installation by Electrical Inspector
- Approval for New Service Connection HT East Discom
- Approval for New Service Connection HT West Discom
- Approval for new service connection LT Central Discom
- Approval for New Service Connection LT East Discom
- Approval for New Service Connection LT West Discom
- CEIG/CEA Approvals of Switchyard Equipment & Transmission Line
- Certificate for successful commissioning
- Charging permission for usage above 132 KV (or above)
- Electricity Connection (Load Sanction)
- Net Metering and Grid Connected Rooftop