Sanction of power supply for construction (on receipt of completed application form and payment of necessary charges), * In case connection is to be released from existing network

This approval is required by an investor for sanction of power supply for construction (on receipt of completed application form and payment of necessary charges), in case connection is to be released from existing network.

DepartmentDepartment of Energy
TypeNew
StagePre-Establishment
Time limit30 Days
FeeNo fee
AppliedApply on the state single window
The department has not published a document list for this approval.