Insights into Company Bills & Payments

State approvals / Maharashtra / Department of Energy

Sanction of power supply for construction (on receipt of completed application form and payment of necessary charges), * Where commissioning of New Sub-station forming a part of the distribution system is required

This approval is required by an investor for sanction of power supply for construction (on receipt of completed application form and payment of necessary charges), where commissioning of New Sub-station forming a part of the distribution system is required.

DepartmentDepartment of Energy
TypeNew
StagePre-Establishment
Time limit365 Days
FeeNo fee
AppliedApply on the state single window
The department has not published a document list for this approval.

More from Department of Energy