State approvals / Assam / Inspectorate of Electricity
Seeking approval for Commissioning of Electrical Generating units.
This approval is required for commissioning of Electrical Generating units
DepartmentInspectorate of Electricity
TypeNew
StagePre-Operation
Time limitWithin 15 days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Copy of “No Objection” or otherwise permission from appropriate owner of the land/ premises, in case the applicant is not the owner | — | Required |
| 2 | Electrical lay out drawings that show the appropriate rating/type/size of all electrical Generators, equipments, accessories, panels etc. including changeover switch/interlocking arrangement in the single line diagram and dimensions / clearances etc. in the physical layout plan & in the details of earthing layout plan | — | Required |
| 3 | Manufacturer’s test certificate of both alternator and engine | — | Required |
| 4 | Structural fitness certificate of the building from the Municipal / Development / Appropriate local Authority and from the Structural Engineer who designed the building structure | If the Generating set is installed at any floor above ground floor of the building | If applicable |
| 5 | NOC from the State Fire Service | If the Generating set is installed at the top of the building | If applicable |
| 6 | Copy of purchase document of Generating set | — | Required |
| 7 | INSULATION TEST RESULT OF AC GENERATOR | — | Required |
| 8 | TEST RESULT OF AC GENERATOR EARTHING | — | Required |
| 9 | CABLE TEST RESULTS | — | Required |
More from Inspectorate of Electricity
- Application for permission to install a lift/ to make additions or alterations to the installed lift
- Application for renewal of license of escalators/lift
- Approval for commencement of power supply in the electrical installations of multi-storied building
- CEIG/CEA Approvals of Switchyard Equipment & Transmission Line
- Certificate for successful commissioning
- Cinema operator license.
- Electrical contractor's license.
- Electricity Connection (Load Sanction)
- License for operating a lift installed before the commencement of the act.
- License for operating a Lift/Escalator
- License for operating an escalator installed before the commencement of the act.
- Obtaining authorization for erection of lifts or escalator.