State approvals / Assam / Inspectorate of Electricity
Seeking approval to commence power supply in overhead line exceeding 650 volts.
This approval is required to commence power supply in overhead lines exceeding 650 volts
DepartmentInspectorate of Electricity
TypeNew
StagePre-Operation
Time limitWithin 15 days
FeeNo fee
AppliedApply on NSWS
Documents to submit
| # | Document | Condition | Required |
|---|---|---|---|
| 1 | Details of earthing | — | Required |
| 2 | Sketch showing details of different type of supports used in the overhead line | — | Required |
| 3 | A sketch of guards provided with dimensions, size of wires along with vertical & horizontal clearances | — | Required |
| 4 | A sketch showing alignment of line indicating positions of sub-stations, supports, CT, PT, circuit breaker, isolator, fuses, gangs, earthing & also roads, rivers and prominent structures along with clearances both vertical & horizontal | — | Required |
| 5 | Copy of Approval of the state government under section 68 of Electricity Act, 2003, in case of overhead line of operating voltage exceeding 11KV; Route map of the overhead line, showing alignment of nearby overhead line | If any, with clearances both vertical and horizontal | If applicable |
| 6 | Copy of No Objection Certificate or otherwise permission from appropriate owner of the land/ premises, in case the applicant is not the owner of any such land/ premises or part thereof that is crossed by the overhead line | — | Required |
| 7 | Copy of Provisional Estimate | — | Required |
| 8 | Copy of PTCC clearance | If the line is in proximity or crosses telecommunication line | If applicable |
| 9 | Authorization Letter | — | Required |
| 10 | TEST REPORTS | — | Required |
| 11 | Cable Test Report | — | Required |
| 12 | Undertaking for any government Schemes | — | Required |
More from Inspectorate of Electricity
- Application for permission to install a lift/ to make additions or alterations to the installed lift
- Application for renewal of license of escalators/lift
- Approval for commencement of power supply in the electrical installations of multi-storied building
- CEIG/CEA Approvals of Switchyard Equipment & Transmission Line
- Certificate for successful commissioning
- Cinema operator license.
- Electrical contractor's license.
- Electricity Connection (Load Sanction)
- License for operating a lift installed before the commencement of the act.
- License for operating a Lift/Escalator
- License for operating an escalator installed before the commencement of the act.
- Obtaining authorization for erection of lifts or escalator.