Insights into Company Bills & Payments

State approvals / Assam / Inspectorate of Electricity

Seeking approval to commence power supply in sub-station exceeding 650 volts.

This approval is required to commence power supply in sub-station exceeding 650 volts

DepartmentInspectorate of Electricity
TypeNew
StagePre-Operation
Time limitWithin 15 days
FeeNo fee
AppliedApply on NSWS

Documents to submit

#DocumentConditionRequired
1 Only dry-type of transformers shall be used for installations inside the residential & commercial buildings — Required
2 Oil filled transformers installed indoors other than in residential or commercial buildings are to be placed at the ground floor or not below the first basement — Required
3 Single line diagram of the installation showing supply & load side — Required
4 Front & Plan view and equipment layout diagrams with dimensions and clearance from nearby structures/buildings — Required
5 A sketch showing earthing system — Required
6 In case of consumers installation, the following Copy of load sanction letter Additional documents are to be furnished If applicable
7 A copy of permission / NOC for construction of the building / installation and approved drawing from Municipal / Development / Appropriate local Authority Additional documents are to be furnished If applicable
8 Copy of No Objection or otherwise permission from appropriate owner of the land/ premises, in case the applicant is not the owner Additional documents are to be furnished If applicable
9 Manufacture test certificate of the Transformer, Circuit Breaker & other prime equipments Additional documents are to be furnished If applicable
10 A detail load schedule of the connected load and test report of the internal electrical installation including earth system with due seal and signature of contractor /authorized person(s) and countersigned by the consumer / owner / occupier or its agent Additional documents are to be furnished If applicable
11 Electrical lay out drawings that show the appropriate ratings / types / sizes of all electrical Generators, equipments, accessories etc. in the single line diagram and dimensions/clearances etc. in the physical layout plan & in the details of earthing layout plan including panels Additional documents are to be furnished If applicable
12 Copy of Provisional Estimate Additional documents are to be furnished If applicable
13 Authorization Letter Additional documents are to be furnished If applicable
14 List of apparatus of voltage Additional documents are to be furnished If applicable
15 TEST REPORT OF APPARATUS OF VOLTAGE Additional documents are to be furnished If applicable
16 Test Report Additional documents are to be furnished If applicable
17 HT/LT Cable Additional documents are to be furnished If applicable
18 Undertaking for any government Scheme Additional documents are to be furnished If applicable

More from Inspectorate of Electricity